GPL says Canefield power to return by 1 PM after grounding transformer fault
Guyana Power and Light says customers served by the Canefield Substation in East Berbice should have electricity back by 1 PM Saturday, after crews traced the fault to the grounding transformer panel.
Foto: GPL/Demerara WavesGuyana Power and Light Inc. (GPL) says electricity for customers served by the Canefield Substation in East Berbice should be restored by 1 PM Saturday, provided no further problems appear during final testing. The utility warned that supply may return to different areas in stages so the network can be brought back safely.
The company traced the outage to an insulation failure in the panel that houses the substation's grounding transformer. Crews are replacing several defective components in that panel, after which the facility will be tested again before power is switched back on.
The grounding transformer is a key piece of safety equipment. It allows the substation's protection systems to detect faults and isolate them quickly. With its panel damaged, the transformer cannot be safely placed in service, and re-energising the network without it would put customers, the public and GPL personnel at risk.
GPL said its technical teams worked around the clock over two days to locate the fault and brought in specialist support to help with the diagnosis. With the cause confirmed, repairs to the panel's insulation are under way.
The utility apologised for the prolonged outage and the hardship it caused households and businesses in East Berbice, and thanked customers for their patience. Thousands of residents in Region Six have been without supply since Friday night.
What customers should know
Affected area: communities served by the Canefield Substation, East Berbice, Region Six. Expected restoration: from 1 PM Saturday, barring complications during final testing. How supply returns: in stages, area by area, rather than all at once. Cause: insulation failure in the grounding transformer panel at the substation.